Water Main & Sewer for New Home or Rennovation

January 16, 2016

When building a new home there are many details and factors included in the pre-construction phase. One of the most important is the water main and sewer system. The water main and sewer installation for new construction are similar when replacing the pipes for an existing structure except the plumbing contractor has to follow a set of plans which are drawn up by an engineer and approved by DOB & DEP.

The first set of plans is for the sewer system and is called SD 1 & 2 AKA Site Connection Proposal Form. The plumbing contractor must follow the details included in these plans for the sewer installation and must obtain DEP inspections upon completion of the new sewer connection.

SD 1 & 2 for new sewer
SD 1&2 for new sewer

2490 Pitkin Ave Sd1&2 "Attachment F"
SD1&2 “Attachment F”

The average new sewer connection will take in-between two and three days for the roadway excavation and piping installation to be completed. At this point the new water main is usually installed.

Digging for new sewer connection
Digging for new sewer connection

Installing new sewer pipe
Installing new sewer pipe

The second set of plans if for the new water main and/or sprinkler main connection. The plumbing contractor requires Cross Connection approval and an approved set of DOB plans before obtaining all required permits.

Cross Connection Plans
Cross Connection Plans

DOB approved plansfor water main
DOB approved plans

Once the permits are released the contractor must schedule a new water main connection with DEP. The new connection is either known as a tap connection or a wet connection, pending the size. The tap connection is for anything 2” or less. The wet connection is for anything 3” or greater.The plumbing contractor is responsible for all excavations and preparing the city main for the new connection, at this point the DEP arrives for 20-30 minutes and installs the new connection.

Wet connection for combined water main
Wet connection

Tap connection for domestic water main
Tap connection

The plumber will then complete the new water main installation, curb valve (if required) and a formal DEP inspection before back-filling the excavations. This process usually takes two to three days as well.

New curb valve & wet connection
New curb valve & wet connection

Installing water main off sets
Installing water main off sets

Keep up with us on Harris Water Main

Does anybody know why Jackman is stuffing the pipe? Emergency Water Main Replacement on Broadway in Manhattan. Watch the whole video on YouTube! Link in Bio!
.
.
.
.
.
#plumberlife #plumbing #plumbinglife #contractor #nyccontractor #backhoe
New construction, New water mains! We love getting to do these projects, all hands on deck! These are some of our favorite projects, which kind of project are yours? New construction or replacement? Watch our latest YouTube video through the link in our bio.
.
.
.
.
#plumbersofinstagram #plumbing #watermain #watermainbreak #contractor #contractorsofinstagram #nyc #nyccontractor #construction #constructionlife
What do you think about this method of installing copper? What are other methods that you use? 

#plumbing #plumbinglife #copperpipe #watermain #watermainbreak #plumberbrooklyn #watermainupgrade
Anyone else feeling this excited for work today? 

#teamharris #plumbinglife  #sewerrepair #watermain
From a 10 Day DEP Notice for a possible issue with the gooseneck to discovering lead pipes, this water main replacement is another one in the bag for our team and another customer with safer and better pipes! Watch the whole video, link in bio!! How do you think we did?
.
.
.
.
#tradesman #constructionwork #contractorofinsta #hardwork #excavation #demolition #bluecollar #harriswater #plumber #plumber #brooklynplumber #nyplumber #brooklyncontractor  #plumbingporn #plumbinghacks #plumbingservice #bluecollarbrotherhood #copperpipe #plumbinglife #plumbingtips #plumberscrack #tradehounds #operatorlife #toolsofthetrade #journeyman #excavatorlife #contractor #backhoe